Day 2 on site


Luckily a very beautiful Kentish day!

The willow weaved plinth wall was lined with waste plastic sheet from the polytunnels. The voids were then filled with bark from the pruning and lined again with another sheet of polythene to act as DPM.

Initial stakes are inserted and the first bales are laid.

Staking down each bale as it is laid for rigidity and to keep the walls in line.


Cross bracing door opening put into place to keep the bales tight and upright.

Losing light on the third course of bales. Time to call it a day

Sunday, 3 March 2013

Day 1 on site

Started on site today with the willow weave plinth wall.

Site all marked out and leveled, ready to go!


weaving the willow in a twining fashion, to get the tightest weave possible for filling.







End of day 1. 
 Early start tomorrow to get the rest of the willow cut and weaved, ready for the straw bales.



Thursday, 24 January 2013

Willow Weaving

For the natural plinth wall, I wish to make the border out of willow weave. 

When this is done properly it looks very neat and beautiful 

I had my first attempt this Christmas....


Little more practice needed.


For the plinth wall we need 150mm of tightly packed willow weave, which I can waterproof and build the bales directly onto.

Using some of the cuttings we had another go at a required height.


This was assisted by some local children.


Even though the snow has halted anything starting on site, I can construct all the elements under cover ready for the quick erection.